0
1
00:00:21,500 --> 00:00:22,260
Hello.
1

2
00:00:22,260 --> 00:00:30,380
After you download a ISPSoft software and after install your ISPsoft software to your computer run
2

3
00:00:30,410 --> 00:00:35,520
your ISPSoft software than this page is going to come to your front.
3

4
00:00:35,520 --> 00:00:38,720
In here we are going to create a new project.
4

5
00:00:38,840 --> 00:00:43,320
You can come here and you can select a file a new and new.
5

6
00:00:43,460 --> 00:00:49,390
Also you can click this icon new icon and this is a confirmation.
6

7
00:00:49,390 --> 00:00:51,200
Are you sure to create a new project.
7

8
00:00:51,230 --> 00:00:52,350
And yes.
8

9
00:00:52,350 --> 00:00:53,200
And we can.
9

10
00:00:53,200 --> 00:00:55,390
write here our project name
10

11
00:00:55,400 --> 00:00:59,390
This is a test project and our controller type.
11

12
00:00:59,390 --> 00:01:11,690
We can select DVP -AH -AH motion - AS -TP and VFD.VFD is for the drives and you can you can write the
12

13
00:01:11,690 --> 00:01:14,000
programs inside of the drives directly.
13

14
00:01:14,000 --> 00:01:21,290
You can send it and drives or vfds are going to run these projects or programs we can select
14

15
00:01:21,290 --> 00:01:29,590
it but we will continue with the DVP series and PLC type I will use SS2 and drive path
15

16
00:01:29,600 --> 00:01:35,990
You can select to your folder inside of your computer where this project is going to save it and where
16

17
00:01:35,990 --> 00:01:43,190
you are going to open this project and okay we adopt our name and controller type and everything and
17

18
00:01:43,190 --> 00:01:46,910
say Okay after you click okay , 
18

19
00:01:46,910 --> 00:01:56,390
New project is going to be open and in here is startup page and let is create a new project come here
19

20
00:01:56,390 --> 00:02:07,010
to program section right click and click new after we need to give to a name to our POU.POU means program
20

21
00:02:07,070 --> 00:02:16,250
organization unit so we can say this is a test section, Test ladder, let's say like this.
21

22
00:02:16,250 --> 00:02:24,800
And task will be cyclic tasks so leave it like this and you can select in here your programming language
22

23
00:02:24,920 --> 00:02:33,610
Ladder diagram or CFC or instruction list so we will use ladder diagram in here and we don't put any
23

24
00:02:33,620 --> 00:02:37,290
password to this project for.
24

25
00:02:37,350 --> 00:02:44,300
For this section for this Pou we are not going to put any password here and say okay.
25

26
00:02:44,300 --> 00:02:46,370
Also we can add here a pou comment.
26

27
00:02:46,580 --> 00:02:57,650
And for example this program section for I/O's and say okay.
27

28
00:02:57,800 --> 00:02:59,930
And you can see it in here.
28

29
00:03:00,050 --> 00:03:08,780
New project is created and we can write our PLC programs from now on to finish.
29

30
00:03:08,780 --> 00:03:10,960
So see you in the next video.